Dental School :

  • As the remediation project moves forward, Zimmer has started removing flex duct and registers and started cleaning in the offices of the 5th floor of the Clinic Building.
    • The 2nd floor has been sealed off while we await the results of the post-remediation inspection and testing. 
    • We are also waiting for the results of air sample testing on the 1st floor. 
  • Boe-Tel has completed the installation of the cable trays for the network infrastructure enhancement project. 
    • They continue to pull new network cable and making connections to marked locations.
  • Schindler Elevator now has power to all three controllers in the Administration Building penthouse. 
  • We have started the process of removing all of the chemicals that were stored in the basement of the Clinic Building.