Dental School :

  • Frischhertz Electric continues to install the 2 ½ inch conduit in the elevator penthouse of the Administration Building for the three disconnects.
  • Boe-Tel is running conduit through the drain thimble next to the drain pipe of the sink for the connection of the network cable on the 3rd floor at every teaching bay.
  • The installation of the cable trays is complete on the 2nd and 3rd floors and continues on the 4th floor.
  • Coastal Air Balance checked the air balance of the 7th and the 8th floor air handling units today.
  • Schindler took Elevators #3 and #4 out of service to change out the interior of the units.  They will also be installing new controllers.
  • BellSouth/AT&T continued their work in the telephone room on the 5th floor.
  • GVA visited to look at the maintenance auto shop, Auxiliary Enterprise warehouse and the safety room in order to address FEMA scope alignment questions.
1542 Tulane Ave.:
  • Ordes installed the starters for the hot water circulating pumps.
  • Stratos Elevator was running power to all three elevators.