Louisiana State University Health Sciences Center Administration & Finance
 

Monday, May 07, 2007

Dental School :

  • C&R Network Communication started running network wires on the 5th floor starting at room 5312, running the wire throughout the 5th floor. 
  • Boe-Tel has a crew working on the 1st, 2nd, 5th, and 6th floors installing cable trays and conduit.
  • Zimmer continues clearing out the demo work in the two auditoriums.
  • Zimmer has also begun their work under the environmental remediation and duct cleaning contract.
    • They are setting up their duct cleaning equipment in the basement.
    • They have started wiping down everything in the stairwells of the Administration Building starting at the basement level.
  • Frischhertz is working in the Administration Building penthouse making the connections for the elevator disconnects.

1542 Tulane Ave. :

  • Ordes was site working on the motor controls for the heating hot water return pumps.
  • Stratos Elevators is working on providing power to Elevators #1 - #3, and lighting in the elevator shafts. 
  • Arc Mechanical continues with demolition work in the basement.