Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, May 09, 2007

Dental School :

  • Frischhertz is continuing to make progress getting power to the elevator disconnects in the Administration Building penthouse. 
  • Boe-Tel worked on the 1st, 2nd and 5th floors of the Clinic Building installing additional conduit. 
  • C&R Network continues making connections in the 5th floor communication closet.

1542 Tulane Ave.:

  • Ordes Electrical starting installing the disconnect panels for the new air compressors.
  • Stratos Elevators is still installing safeties and lights on Elevator #3.
  • ARC Mechanical is installing a pressure relief valve on the main steam line.

Irrigation Project: 

  • Two additional stations (zones) have been piped.  A total of thirteen stations have been completed.
  • The main for Lions/LSU Clinic and a portion of the CSRB irrigation system has been connected to the water source and is now operating.