Louisiana State University Health Sciences Center Administration & Finance
 

Monday, June 25, 2007

NOTICE:  There will be a condenser water outage in the Medical Education Building on Thursday, June 28th from 3:30 PM until 11:30 PM.  The condenser water system provides cooling for the walk-in freezers and coolers throughout the building.  Both towers will be shut down between 3:30 PM and 6:30 PM.  One of the towers will be operating by 6:30 PM and the other will be operating by 11:30 PM.  While the coolers and freezers are without condenser water, they will not maintain their appropriate temperature.  The piping is being replaced to improve reliability. 

Dental School :

  • The replacement of the ceiling grid and tile continues to move forward.
    • Grid and tile installation continues on floors 2 through 7 in the Clinic Building .
    • The sprinkler subcontractor continues to reposition sprinkler heads on the 5th and 6th floors.
    • HVAC flex ducts and diffusers are being installed on the 6th floor.
  • The project to complete the final remediation and duct cleaning is nearing completion.
    • The Administration 2nd floor sample results indicated some areas need to be re-cleaned. 
      • The breezeway from the Clinic Building to the Administration Building was one of the areas, and the containment will remain in place on the 2nd floor  until the re-cleaning is complete and new sample results come back later in the week.
    • Area sample results for the 3rd and 4th floors in the Administration building came back clean. 
      • The containment will be removed.
  • The construction of the new network/telecom closets is continuing.
    • All of the coring is complete and sleeves have been installed on floors 2 through 7 in the Clinic building. 
    • The build out of the closets themselves and the installation of new racks in the closets is underway throughout the building. 
  • The replacement of the flood damaged 1st floor exit doors has begun.

1542 Tulane Ave.:

  • Ordes successfully tied-in a sub-panel that feeds power to all "LNA panels" which provides power to lights and receptacles in the NE quadrant of the building.

Landscaping Project

  • Despite the rain, a long string of serpentine landscape edging was installed in the memorial bench area. 
  • Planting continued on the Gravier St. side of the Lions/LSU Clinic Building and on the Perdido St. side of the CSRB. 
  • Work in the afternoon switched from planting to cleanup from the rain.