Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, September 11, 2007

Dental School :

  • 1st Floor
    • lighting installation in elevator lobby is nearly complete.
    • furdown is ready for sheetrock and Landis is awaiting materials.
  • Sterilizer
    • Installation continues.
  • Miscellaneous
    • Damper replacement will re-commence on Thursday evening.

1542 Tulane Ave :

  • Ordes Electric continues to run control wiring for the new controls.
  • Arc Mechanical continues to label insulated pipe in the basement. The contractor is labeling the hot water supply and return lines.
  • Stratos Elevator Co continues to wire elevator #2 and is scheduling a run-test for elevator #2 this evening. The contractor is also replacing the motor wiring for elevators #7 & #8.
  • Siemens continues to install new fire alarm device boxes on the 3rd floor.
  • American Sprinkler Co is on site making final repairs to the fire pump.