Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, September 26, 2007

Dental School:

  • The walls in the 1st Floor lobby area of the Clinic Building are being taped and floated.
    • The lighting installation continues.
    • Electrical connections continue to be made throughout the 1st floor spaces.
  • Landis is prepping to execute the change order to reposition the sterilizer shut off valves and intall the additional air line in Central Sterilization.

1542 Tulane Ave.:

  • Stratos is removing the buffers on Elevator #8.
  • Siemens finished installing conduit to the fire alarm device boxes in the basement. 
    • They are now installing conduit on the 2nd floor.
    • The contractor completed the installation of fire alarm device boxes on Floors 9 and 10.

Campus Sidewalk Upgrades:

  • Boh Bros poured the concrete for the Residence Hall sidewalk along Perdido Street and S Roman Street.  
    • This completes the concrete pouring on this project.

MEB Cafeteria:

  • The terrazzo base has been installed. 
  • Merit Sprinkler is scheduled to relocate the one sprinkler head that is in conflict with the feature wall installation.
  • Custom casework is being installed as it arrives on site.

Morgue Cooler Project:

  • New cooler panels continue to be received from the manufacturer and installed. 
  • The refrigeration lines and condenser water lines have been run to each condenser unit and these have been insulated. 
    • The control panels for each condenser unit have also been hung.

Landscaping Project:

  • Crews completed the installation of irrigation station # 3 on the Gravier St. side of the Allied Health/Nursing Building.
  • They have installed most of the piping for irrigation stations #4 and #5 at the corner of Gravier St. & Bolivar St. 
  • They continued to complete the final grading on the Gravier St. side of the Allied Health/Nursing Building closer to S. Roman St .