Louisiana State University Health Sciences Center Administration & Finance
 

Friday, October 26, 2007

Dental School :

  • The installation of the curved ceiling in the 1st floor Clinic Building lobby is proceeding.
    • All of the locksets for the 1st floor doors have been installed.
  • Landis has begun painting the refinished walls in the 2nd floor Administration Building conference room.
    • The duct work installation continues.
  • Schindler ran wiring for the controls to Elevators #3 and #4.
    • Schindler discovered a bad control board on the controls for the freight elevator.  A replacement has been ordered.

Allied Health/Nursing Flooring Enhancement:

  • All of new tile has been installed on the 7th floor elevator lobby and corridors. 
    • The wall base will be installed this evening.

1542 Tulane Ave. :

  • Ordes finished running the new wiring for the Energy Transfer Station pressure switches.
  • Stratos Elevator continues to work on Elevators #1 and #8.
  • Siemens finished installing the new fire alarm speakers and strobes on the 1st floor and mezzanine. 
    • They will begin installing new speakers and strobes on the 8th floor this weekend.
  • The painting contractor finished sanding in stairwell C and will continue sealing the walls with primer this weekend.
  • LSUHSC Facility Services staged supplies on the 7th and 8th floors to prepare for the packing of offices that will start on Monday.