1542 Tulane Ave. :

  • Ordes Electric removed the electronic controls for the surge tank. 
  • Siemens finished installing the new wiring and fire alarm devices on Floors 9 and 10.
    • They are removing the old wiring on those floors.
  • Stratos Elevator installed the new platform for Elevator #7.
    • They are changing the governor sheaves and governor cables for Elevator #8.
    • Stratos resumed work on Elevator #1 and is welding the elevator frame.
  • Remediation, Duct Cleaning, et al.
    • Zimmer-Eschette completed the duct cleaning on the 1st Floor and samples will be taken tomorrow.
      • The duct cleaning crew is currently cleaning the ducts on the 8th Floor. 
    • Zimmer removed the damaged carpet on the 1st and 8th Floors.
    • The contractor is removing debris from Floors 6 and 7.
    • Zimmer is removing the paint and cleaning Suite 123 on the 1st floor.

Dental School :

  • Landis continues to touch-up the sheetrock walls, fur downs, and ceilings on the 1st Floor of the Clinic Building.
  • Siemens began connecting the controls for the damper controlling the 2nd Floor conference room area in the Administration Building .
    • Landis completed refinishing the walls that required touch-up.
    • The linear diffusers are installed
  • The hoist way wires were removed from Elevators # 3 and #4.
    • The Elevator # 8 front finishes including the doors and stainless steel panels were removed to prepare for the interior upgrades. 

Landscaping Project:

  • Crews cleaned, repaired and mulched the planting beds on the S. Prieur St. and Gravier St. side of the Lions/LSU Clinic Building.
  • They mulched the Algerian ivy beds on the Bolivar St. side of the Allied Health/Nursing Building.