Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, June 26, 2008

1542 Tulane Ave. :

  • The contractor is painting the ceiling and walls in the elevator lobby on the 1st Floor.
  • Securitas is installing conduit and card readers at the loading dock on the 1st Floor.
  • Hogue & Associates are removing ballasts from old light fixtures.

Dental School :

  • The wood nailers for the parapet wall copings have been installed on the Clinic and Administration Buildings.
    • Needham Roofing is waiting for the metal to install the coping on the parapet walls. 
  • Needham repaired 4 small vents that were damaged on the Clinic Building roof. 
    • They started working on correcting the minor damages that occurred during the project; ruts in the grass, damaged curbs, etc.