Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, July 02, 2008

1542 Tulane Ave. :

  • Siemens is installing the duct mounted smoke detectors in the HVAC ductwork.
  • The contractor finished painting Room 114.
    • Painting continues in Room 100.
  • Securitas began pulling wiring through the new conduit that has been installed for the card readers on the 1st Floor.
  • Hogue & Associates continue to remove ballasts from old light fixtures and dispose of the old fixtures.
    • Floors 6 through 8 have been cleared.
  • Premier Source Inc. is prepping the 4th Floor for honing of the terrazzo.

Residence Hall Renovations:

  • The remaining demolition is on hold while waiting for the closure of the walkway at the exterior balcony.
  • New duct work is being installed and connected to the air handling unit that has been installed on the mezzanine.

MDL #5 Renovations:

  • The contractor is framing up the partition above the ceiling that will assist with noise reduction.

MEB Lecture A & B Enhancements:

  • Trison continues to remove concrete and has begun to install the floor duct and seal tight conduit for the new podium.

Dental School :

  • Premier Source Inc. continues to hone the 6th Floor terrazzo.