Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, September 11, 2008

1542 TULANE AVE.:

  • General contractor continued demolition in the 3rd and 4th floor annex.
  • Elevator contractor continued work on elevator #4.
  • Security contractor continued preparations for camera installation.
  • Contractor installed support bracing for ceiling lights in the rear elevator lobbies on 5th, 6th and 7th floors.
  • Facility Services continued installing new fan coil units on the 6th floor.  -Work continued on installation of restroom accessories throughout the building.
  • Work continued roughing in plumbing in the 6th and 7th floor lounges for the new kitchenettes. 
  • DENTAL CAMPUS 6th and 8th FLOOR RENOVATIONS
  • Contractor continued laying-out coring locations for piping penetrations---Coring has begun in room 8405.

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • Contractor finished removing the support beams for the accordion walls
  • Mechanical Contractor is insulating ductwork and piping in Auditorium A.
  • Contractor resumed construction of the ceiling framing in Auditorium B.
LIBRARY COMMONS:
  • Contractor continues with the plumbing for the coffee Kiosk.
  • Contractor framed the drywall ceiling above the coffee Kiosk.
  • Facilities Services continued rough in for lights.

LIONS BUILDING MITIGATION:

  • Mechanical Sub-Contractor is running lines for the new Med Gas on the 6th floor simulation rooms.
  • Mechanical Sub-Contractor is running supply duct on the Gravier side of the 6th floor.
  • Mechanical Sub-Contractor is insulating the heating hot water lines on the Bolivar/CSRB side of the 6th floor.  They are also insulating the supply duct following the installation on the Gravier side of the floor on 6 and also on 7th floor.
  • Mechanical Sub-Contractor finished raising the existing waste lines that are below the new ceiling height on the 6th floor.
  • Mechanical Sub-Contractor is piping in the waste lines and the vents for the water closet carriers and urinals in the bathrooms on the Bolivar side of the 6th floor.
  • Mechanical Sub-Contractor is piping in the AHU in the mechanical room on the 1st floor on the Gravier/Bolivar side of the building.
  • Electrical Sub-Contractor is terminating the wire to the new panel boxes on the 2nd floor in the new electrical room on the CSRB side.
  • Iron Sub-Contractor started erecting the steel beams for the first 2 floors of the new stairwell. 
  • Contractor is painting the walls on the 7th floor of the new lab.

MDL-5 LAB RENOVATION:

  • Contractor is patching wall for new paint.
  • Contractor continues installing casework.

MEB 2nd FLOOR LOBBY:

  • Contractor painted the ceiling of the area last night.

MEB 4th FLOOR CEILING REPLACEMENT:

  • Contractor installed supply air grilles. 80% complete.