Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, October 2, 2008

 

1542 TULANE AVE. :

  • The general contractor completed the drywall ceiling installation in Room 718.
  • They continued installing new suspended ceiling grid in the 8th and 7th Floor elevator lobbies. 
  • The walls in the 4th Floor lounge have been dry walled.
  • Crews continued installing walls in the 5th and 6th Floor lounges.
  • The painting contractor completed painting offices on the 8th Floor and continued painting offices on the 5th through 7th Floors. 
  • The electrical contractor continues installing new recessed light fixtures in conference rooms on the 5th through the 7th Floors.
  • The flooring contractor continues carpet repair and installation in rooms on the 6th Floor and floor tile installation in stairwells and the restroom alcoves.
  • LSUHSC Facility Services completed installing irrigation piping in the front of the building.
    • They ran the electrical conduit for the new bollards (sidewalk lights).

 

DENTAL CAMPUS AUDITORIUM A & B RENOVATIONS:

  • The electrical sub-contractor is installing whips and continues to install conduit rough-ins for the lighting in Auditorium A.

 

DENTAL CAMPUS ROOF REPLACEMENT:

  • The contractor is repairing flashing and is caulking around the perimeter of the Clinic Building penthouse.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The installation of gas lines for the peninsulas in Room 8405 is progressing.
  • Electrical sub-contractor is pulling wiring for the new electrical outlets.

 

LIBRARY COMMONS:

  • The contractor is installing metal support tubes for the rollup fire door at the passenger elevators on the north side.
  • LSUHSC electricians are running conduit for the light fixtures near the center stairs.
  • LSUHSC plumbers continue to rough in the plumbing in the janitors closet.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical sub-contractor is insulating supply duct and heating hot water lines on the Gravier St. and the CSRB side of the 6th Floor.
    • They continue to pipe in the VAV on the 6th Floor and run supply duct in the 1st Floor mechanical room.
  • The electrical sub-contractor is installing electrical outlets on the new CMU walls on the 1st Floor and pulling new data wires on the 6th Floor.
  • Iron sub-contractor is welding the taps on the steel structure on the 3rd and 4th Floors for the new stairwell.
    • They are installing the supports for the removable wall panels in the large lecture room.
  • The sprinkler sub-contractor is relocating sprinkler heads on the Gravier St. side of the 6th Floor.
  • The contractor is installing floor tiles on the 7th Floor in the small rooms of the new lab.
    • The ceiling grid on the CSRB side of the 6th Floor is being hung.
    • A crew is installing ceiling wire on the CSRB side of the 6th Floor.
    • They continue hanging door frames on the CSRB side of the 6th Floor.
    • A crew is sealing wall penetrations on the Gravier St. side of the 6th Floor.
    • Sheetrock is being hung by the simulation rooms on the 6th Floor.
    • CMU walls are being constructed on the 1st Floor on the S. Prieur St. side of the building. 

 

MEB MDL-5 LAB RENOVATIONS:

  • The plumbing sub-contractor completed reconnecting acid waste drain lines for the epoxy sinks in the main MDL room.
  • They continue to rough-in the plumbing in Room 4109 for the nine stainless steel sinks.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor is framing the fur down between the lecture halls.