Louisiana State University Health Sciences Center Administration & Finance
 

Friday, October 24, 2008

 

1542 TULANE AVE. :

  • The general contractor continued drywall repairs in offices on the 2nd and 3rd Floors.  
  • They installed suspended ceiling grid in the lounges on the 6th and 7th Floors and started installation of ceiling grid in the lounges on the 4th and 5th Floors. 
  • The electrical contractor continued installing new light fixtures in hallways and stairwells. 
  • The furniture vendor continued arranging furniture in offices on the 5th Floor.
  • The construction cleaning contractor shampooed the 7th Floor office carpets.
    • They continued cleaning on the 7th and 6th Floors.
    • Crews returned to cleaned areas that failed inspection on the 8th Floor. 
  • Facility Services continued to work on punch list items on floors 5 to 8.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor installed wood supports for the baseboards in Auditorium A along the south wall and installed insulation on the east and south walls of Auditorium A. 
  • The electrical contractor installed wiring and conduit for the walls in Auditorium A. 
  • The contractor installed metal framing for the soffit and ceiling in Auditorium B.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The mechanical contractor installed horizontal gas and vacuum piping inside the interior walls of the tissue culture room in Room 8405J.
    • They installed the drain line for the fume hood in Room 6335.
  • The general contractor removed the door and frame at the south entrance of Room 8405.
    • They framed the exterior wall for Room 8405K and the south entrance of Room 8405.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor installed three sinks and faucets in the 7th Floor lab.
    • The plumbers continued to rough in the waste, vent, and domestic water lines for the urinals and the toilets in the bathroom on the 1st Floor. 
  • The iron subcontractor welded the decking for the roof and saddles on the 4th and 6th Floor. 
  • The casework subcontractor installed four base cabinets and six countertops in the 7th Floor lab space.
  • The contractor installed additional fur downs on the 6th Floor.
    • They continued to tape and float the fur downs on the CSRB side of the 6th Floor.
    • A crew installed tile floor at the entry way of the new lab on the 7th Floor. 

 

MEB MDL-5 LAB RENOVATIONS:

  • The contractor installed electrical receptacles for the pedestal frames in the MDL room.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed ceiling grid on the Roman St. side of the lobby. 
  • The mechanical subcontractor removed the existing supply and return air ductwork. 

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor grouted the new tiles that have been laid between the A and B Towers.