Louisiana State University Health Sciences Center Administration & Finance
 

Monday, November 10, 2008

 

1542 TULANE AVE. :

  • The general contractor continued making wall repairs in Room 545 and in various offices on the 2nd Floor. 
  • The electrical contractor installed new light fixtures on the front porch and continued installing light fixtures in conference rooms on the 2nd and 3rd Floors. 
    • Preparations continue for installation of the new light fixtures in the 1st floor lobby. 
  • The construction cleaning contractor continued cleaning offices on the 5th Floor and restrooms on the 7th Floor. 
  • The mechanical contractor continued installing and insulating air conditioning ducting in the lounges on the 3rd, 4th, and 5th Floors.   
  • Facility Services continued minor repairs on various floors.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor installed wire mesh and foam anchors for the riser seating in Auditorium A. 
  • The contractor installed additional sheetrock in the ceiling troughs in Auditorium B.
  • The electrical contractor installed wiring for the down lights in Auditorium B.

 

DENTAL CAMPUS 6th & 8th FLOOR LAB RENOVATIONS:

  • The contractor caulked joints for all the exterior masonry walls in Suite 8405 .

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued planting shrubs and spread mulch in the planting beds in front of 1542 Tulane Ave.

 

LIBRARY COMMONS: 

  • The contractor installed wall tiles on the frieze wall, sprinkler pipes in the mechanical room, and ceiling grid in the study area.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor installed eyewash and emergency shower signage on the 7th Floor.
    • They insulated supply air ductwork on the northeast side of the 6th Floor.
    • Crews insulated domestic water lines on the east side of the 1st Floor.
  • The steel subcontractor welded clips on the 2nd Floor and the roof of the stair tower.
  • The electrical subcontractor finished installing the electrical receptacles for the lab on the 7th Floor.
    • Another crew moved the transformer on the 2nd Floor.
  • The sprinkler subcontractor moved sprinkler heads on the northwest side of the 6th Floor.
    • They installed fire pump valves on the 2nd Floor. 
  • The contractor installed sheetrock on the bulkhead on the northeast side of the 6th Floor.
    • A crew installed studs on the 2nd Floor between the electrical and telephone room and plastered the CMU walls on the east side of the 1st Floor.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor installed the new mailboxes.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The mechanical contractor installed supply ductwork for the restrooms and lobby space. 

 

MEB 6109 & 6148 LAB RENOVATIONS:  This is a new project that will renovate a research lab at the MEB.  Included in the scope of work are new ceilings, flooring, and lab countertops.

  • The contractor removed ceiling grids, ceiling tiles, and HVAC grills.