Louisiana State University Health Sciences Center Administration & Finance
 

Monday, November 24, 2008

 

1542 TULANE AVE. :

  • The construction cleaning contractor continued cleaning the stairwells and restrooms on all floors.
  • The elevator contractor continued removing the protective film on Elevator 8.
  • The flooring contractor installed floor tile in the kitchenettes in the 7th Floor lounge.
  • The furniture vendor completed installing cabinets and setting up chairs and tables in the lounge on the 7th Floor.
  • The network wiring contractor continued new data wiring on the 6th Floor. 
  • Facility Services continued making minor repairs on various floors.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The general contractor finished priming the walls in Auditorium A. 
  • The contractor framed the stairs for Auditorium B.
  • The mechanical contractor connected chilled water supply and return lines to the new AHUs.

 

DENTAL SCHOOL 6th & 8th FLOOR LAB RENOVATIONS:

  • The electrical contractor installed conduit for the data outlets in Room 6335.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued removing sandbags from around buildings at the downtown campus.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor insulated chill water lines, heating hot water lines, and supply lines on the east side of the 1st Floor.
    • They installed roof drains on the exterior stairwell tower.
    • Crews notched the fire door duct on the north side of the 5th Floor.
  • The electrical subcontractor grounded service entrance cable on the west side of the 1st Floor.
    • Electricians crimped 32 feeders to allow for termination to the new switchgear on the 2nd Floor.
    • They installed wire for the fire alarm devices on the south side of the 6th Floor.
  • The fireproofing subcontractor primed saddles on the 1st – 3rd Floors of the exterior stairwell tower. 
  • The contractor taped and floated the fur downs and monitor recesses on the 6th Floor, north side.
    • Crews framed windows on the northwest side of the 6th Floor.
    • Carpenters constructed new walls on the 2nd Floor and installed CMU on the 1st Floor, west side.

 

MEB MDL 6 RENOVATIONS:

  • The project to renovate Multidisciplinary Lab 6 has gotten underway.  The renovations to this lab will follow the model established in the renovation of MDL #5.
  • The contractor removed existing ceiling tiles, equipment, and disconnected electrical and plumbing for demolition.