NOTICE:  On Friday, January 16th, there will be service outages in the Medical Education Building from 6:00 PM until midnight.  There will be no domestic hot or cold water on the 4th, 5th and 6th floors of the MEB, and no de-ionized water in the entire building. 

 

During the outage, there will be no water at any faucet, toilet or urinal on the MEB 4th, 5th and 6th floors and we ask that these services not be used.  Also, there will be no de-ionized water at any service location in the MEB.  We ask that the valves remain closed on this system during this outage to avoid damage upon re-energizing the equipment.   

 

Construction progress in the MDL 6 and on the 5th and 6th floors necessitates these outages.

 

NOTICE:  There will be a partial building power outage at the Lions/LSU Clinics Building on Saturday, January 17th, from 6:00 AM to 6:00 PM.  This outage will affect receptacles and lighting on the west half ( S. Prieur Street side) of the building.  During the outage there will be emergency power to maintain emergency lights and service to some specific equipment in the building – these items are plugged into red receptacles.  The regular receptacles and lights will be off in sections of the S. Prieur Street side of the building as the electrical riser is shut down for this work. 

 

Please note that only the equipment already plugged into the red receptacles should be plugged into them.  Plugging in additional pieces of equipment will cause all equipment to fail if circuits are overloaded. 

 

Air conditioning, exhaust, and pumping will not be affected, as their power source will not be shut down.

 

1542 TULANE AVE. :

  • The general contractor started painting the walls in Room 443, continued patching holes on the 2nd and 3rd Floors, and framing new walls in the 2nd Floor lounge. 
  • The electrical contractor installed new light fixtures in the 2nd Floor hallway.
  • Facility Services continued painting offices and hallways on the 4th Floor, installed temporary wood floors in Elevators 7 and 8, and worked on minor repairs on Floors 5 to 8.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed the down lights in Auditorium B.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The contractor taped and floated the walls in Rooms 6333, 6335, and 8405.

 

EXTERIOR/LANDSCAPING:

  • Facility Services installed irrigation piping and sprinklers beside the Resource Center .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The electrical subcontractor installed the buss duct tap box for the B riser.
  • The mechanical subcontractor began installing control wire to the VAV boxes on the CSRB side of the 6th Floor.
    • Crews are installing heating hot water piping and supply duct on the 6th Floor, Bolivar Street side.
    • They installed medical gas outlet boxes in the simulation rooms and insulated heating hot and chilled water lines on the Bolivar St. side of the 1st Floor.
  • The contractor repaired the roof of main building.
    • They continue to install studs for the fur downs on the 6th Floor, Bolivar St. side.
    • Crews installed ceiling tiles in the middle hallways on the 6th Floor and on the 2nd Floor, CSRB side.

 

LIBRARY COMMONS:

  • LSUHSC electricians installed additional light fixtures in the cafe.

 

MEB 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor removed old ceiling wire from middle of the lobby.

 

MEB MDL 6 RENOVATIONS:

  • The contractor wired light fixtures in the main MDL room.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The general contractor continued to frame walls in the administrative area. 
  • The electrical contractor continued to run conduit in the laboratory area. 

           

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor continued installing exterior mullion trim. 
  • A crew installed sheetrock for the soffit along the Perdido Street side of the A & B Towers.
  • The contractor installed the stud frame for the soffit on the corner of S. Roman St. and Perdido St .