Tuesday, February 10, 2009

 

1542 TULANE AVE. :

  • The general contractor began installing new sprinkler piping in the 2nd Floor lounge.
    • Crews continued framing walls and fur downs in the 1st Floor lounge and patching holes in offices on the 2nd and 3rd Floors. 
  • The mechanical contractor continued piping new fan coil units on the 2nd and 3rd Floors. 
  • LSUHSC Facility Services continued painting offices and hallways on the 4th Floor and pressure washing the Lakeside Lot.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The contractor completed installing ceiling tiles on the 6th and 8th Floors.

 

EXTERIOR/LANDSCAPING:

  • The contractor continued planting shrubs and began installing the new fence around the well at the corner of Gravier St. and S Claiborne Ave.
  • LSUHSC Facility Services continued installation of irrigation piping behind the Resource Center at the corner of S. Prieur and Gravier Sts.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:        

  • The contractor continued installing curtain wall mullions on the 2nd through 5th Floors of the exterior stairwell.    
  • The contractor continued installing studs for the fur down in the 6th Floor elevator lobby and work on the Reception Center fur down the 6th Floor.
    • A crew continues to clean the stone floors on the 1st Floor. 
  • The electrical subcontractor pulled more wire for receptacles on the 6th Floor.
    • They ran additional conduit and pulled wire for lights on the 6th Floor, Gravier St./Bolivar St. side.
    • Electricians continue to run conduit on the 9th Floor from the hallway to room 908.
  • The mechanical subcontractor insulated chill water supply and return lines on the 1st Floor, Bolivar Street side.
    • A crew continues installing fire dampers on the 2nd Floor.

 

LIBRARY COMMONS:

  • LSU electricians completed installing the lights above the coffee kiosk. 

 

MEB MDL 6 RENOVATIONS:

  • The contractor completed installing VCT tiles in the corner rooms.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The general contractor continued hanging sheetrock in the administrative area and taping and floating the lab area.
  • The electrical contractor pulled wire in the administrative area. 

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor painted underneath the store front windows and installed the metal frame for the exterior sliding glass door on the Bolivar Street side.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor continued installing linear diffusers in the corner lobby. 
  • The mechanical contractor installed hard duct near Elevator B and ran roof drain pipes near the walkway.