Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MARCH 20, 2009

 

1542 TULANE AVE.:

  • The general contractor continued painting in Rooms 109H, 111 and 111A, and continued the ceiling work in 111. 
  • The furniture vendor relocated modular furniture and surveyed the 2nd and 3rd Floors in preparation for installing furniture. 
  • The painting contractor continued painting offices on the 2nd Floor. 
  • LSUHSC Facility Services continued making repairs on the 1st and 3rd Floors.

 

EXTERIOR/LANDSCAPING:

  • Facility Services conducted landscape maintenance in preparation for Family Day.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The contractor installed the elevator lobby storefront.
  • Crews installed cove base in the 6th Floor conference rooms on the CSRB side.
  • They continued installing laminate on the fur down in the computer lounge area, carpet in the large conference room and floor tile in the computer lounge. Workers completed installing window frames by the new stairwell door on the 6th Floor, Gravier Street side.
  • The installation of exterior granite on the 3rd and 4th levels of the new stairwell continued.
  • Workers continued framing the wall near the 5th Floor for the new stairwell.

 

LIBRARY COMMONS:

  • Contractor continued installation of the display cases. 
  • They completed the installation of the ceiling trim for the wood ceilings. 
  • LSUHSC Facility Services continued installing light switches and completed the plumbing.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing lights and outlets along the walls and patched sheetrock.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor modified sprinkler heads in the administrative area. 
  • The flooring contractor continued installing VCT in the lab area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor continued taping and floating the fur down in back lobby area of Tower A.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The fire alarm contractor pulled wire for new devices in Rooms 8405A and 8405B.
  • The mechanical contractor installed safety showers in Rooms 8405A and 8405B and connected the fume hood utilities in Room 6335

 

DENTAL 4TH FLOOR AUDITORIUM RENOVATIONS:

  • The sprinkler contractor removed existing sprinkler pipe.

 

ALLIED HEALTH/NURSING ROOF REPLACEMENT:

  • The contractor installed the first ply of the new roofing material on the elevator penthouse. 
  • The contractor removed the old roofing system from the stair penthouse and installed the insulation.