Louisiana State University Health Sciences Center Administration & Finance
 

Friday, March 27, 2009

 

1542 TULANE AVE. :

  • The general contractor completed work in Rooms 109H, 111 and 111A.
    • Demolition continued in Rooms 341, 342 and 343.
    • Workers continued hanging drywall in the 2nd Floor lounge.
    • They are making wall repairs in Rooms 235K and 235M. 
  • The electrical contractor continued electrical rough-in for lighting in the 1st Floor lounge.
  • LSUHSC Facility Services continued painting and making electrical repairs on the 1st and 3rd Floors.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:  

  • The contractor installed glass in the storefront wall between the computer lounge and the new stairwell.
    • Workers plastered the 1st Floor restroom walls on the Bolivar Street side of the building.
    • They finished installing ceiling grid in the 1st Floor elevator lobby.
    • Crews continued painting the plaster walls on the CSRB side of the 1st Floor.
    • The installation of the block walls in the freight elevator shaft on the 1st Floor continues.
    • Additional carpet was installed on the 6th Floor, Bolivar Street side.
    • Workers installed granite on the 1st Floor.
  • The electrical contractor terminated phone wires at the patch panels in the 6th Floor telephone/data closet. 
  • The mechanical contractor installed copper tubing to control the chilled water valves for the AHU on the 6th Floor, Bolivar Street side.
  • AT&T continues to work on the installing the new telephone feeder cable.

 

LIBRARY COMMONS:

  • The contractor continues to trim out the display cases.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor finished moving receptacles in the walls for the wall panel installation.

 

MEB MDL 6 RENOVATIONS:

  • The general contractor worked on punch list items.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor floated the floors in the lab area and part of the administrative area. 
  • Workers continued to install VCT in the lab area. 
  • The contractor installed the sheetrock ceiling for the animal care room.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor framed the fur down in the mezzanine level between the B & C Towers .
  • The mechanical contractor installed plenum boxes along the storefront wall in the extended lobby area.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor wired the ballasts for the wall-mounted light fixtures in Auditorium B.

 

DENTAL 6th & 8th FLOOR LAB RENOVATIONS:

  • The fire alarm contractor installed the new fire alarm devices in Room 6335.