Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, APRIL 24, 2009

 

1542 TULANE AVE. :

  • The general contractor continued finishing drywall in the 1st Floor lounge.
    • Workers started installing ceiling grid in the 1st Floor lounge.
    • Crews continue painting the auditorium.
  • The ceiling grid contractor completed repairs to the 3rd Floor hallway ceiling.
    • They continued repairing the 2nd Floor front hallway ceiling.
  • The cleaning contractor continued cleaning offices on the 3rd Floor along the center hallway and began cleaning the front hallway. 
  • Facility Services continued making electrical repairs on the 1st and 3rd Floors and painting rooms on the 2nd and 3rd Floors.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:  

  • The contractor began installing trim for the windows of the stair tower at the 6th level.
    • They painted the mechanical room on the 1st Floor, Bolivar Street side.
    • Workers sealed the original penetrations in the 6th Floor computer lounge.
    • Crews continued framing and sheet rocking the shaft walls of the stairwell at the 3rd level.
    • They continued to waterproof the granite wall panels on the new stairwell.
    • The contractor continued the installation of CMU walls in existing telephone room.
  • The electrical contractor installed a junction box for the new fiber cables on the 6th Floor, Bolivar Street side.
    • They continued wiring the firemans switch for the exhaust fans in the new stairwell and installed the door closure on the 6th Floor Gravier Street side.
  • Stryker is installing microphones in the large lecture room on the 6th Floor.

 

LIBRARY COMMONS:

  • LSUHSC electricians relocated light fixtures above the magazine racks.

 

MDL-3 RENOVATIONS:

  • The contractor completed demolition in the MDL.
  • The abatement contractor began preparation for abatement over the weekend.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor installed ceiling grid for the sheetrock ceiling underneath the mezzanine level of the A & B Towers and in the expanded lobby area.
  • They installed ceiling grid for the acoustical ceiling between the B & C Towers .

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor began installing new metal around the elevators.
  • The wall panel contractor finished installing wall panels along the Medical Center Stores wall.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor continued installing receptacle raceways in the laboratory area.
  • The contractor continued connecting drains to the sinks and installed plumbing fixtures in the laboratory area. 

 

ALLIED HEALTH/NURSING RE-ROOFING PROJECT:

  • The contractor continued installing insulation and a cap on S. Roman street side of the roof.  There are eight feet remaining.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor completed installing additional conduit and junction boxes in the crosswalk outside Room 4202.