Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JUNE 8, 2009

 

1542 TULANE AVE.:

  • The electrical contractor installed the new up-lights and lighted bollards along Tulane Ave.
  • Facility Services continues to install and connect fan coils in offices on the 2nd Floor. 

 

EXTERIOR/LANDSCAPING:

  • Facility Services planted sod in front of the Allied Health/Nursing Bldg. and spot patched sod at various areas on the downtown campus.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The mechanical contractor finished piping the fuel lines to the new fuel tank. 
  • The electrical contractor removed underground wires from the old generator room and switchgear room on the 1st Floor.

 

LIBRARY COMMONS:

  • The coffee kiosk passed the health inspection.

 

LIONS BUILDING 8th FLOOR NETWORK CLOSET:

  • The contractor continued taping and floating the network closet.
  • The mechanical contractor installed chilled water supply and return lines from the mechanical room to the network closet. 

 

RESIDENCE HALL 2ND FLOOR LOBBY EXPANSION:

  • The interior contractor taped and floated the gypsum board ceiling under the mezzanine between the A and B Towers. 
  • Workers installed ceiling tiles between the B & C Towers .  
  • Crews continued taping and floating the gypsum board ceiling in the expanded lobby area. 

 

ALLIED HEALTH/NURSING BLDG. RE-ROOFING PROJECT:

  • The contractor installed aluminum flashing along the MEB side of the roof.
  • They completed installing the white cap sheet. 
  • Workers removed and replaced the existing roof on the front entry way to the building on Sunday.     

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continues to monitor and make adjustments to the temporary air conditioning units for the 6th and 7th Floors Quadrant D.
  • The contractor completed insulating the heating hot water and chilled water piping and continued connecting building automation controls for AHU 6D. 
  • The contractor completed insulating the chilled water piping, continued insulating heating hot water piping, and continued connecting building automation controls for AHU 7D.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed metal trim for the wood wall panels by the door to the right of Lecture Hall A.

 

MEB MDL #3 RENOVATIONS:

  • The contractor poured self leveling concrete on the floor in the main MDL room.

 

MEB PHARMACOLOGY RENOVATIONS:

  • The contractor waxed the floors in the admin section.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The contractor installed additional acoustical panels on the west wall and additional framing along the east wall of Auditorium B. 
  • The AV contractor installed the projection screen framing in Auditorium A.

 

DENTAL SCHOOL PARKING LOT AND ROAD REPAIRS:

  • Contractor completed paving the Moss Street entrance driveway and the other asphalt repairs around the campus. 
  • Concrete driveway aprons were completed at the Army Parkway, Moss Street and the Clinic Building service entrance.