1542 TULANE AVE. :

  • The cleaning contractor cleaned offices on the 2nd Floor along the center corridor. 
  • Facility Services painted the stage trim in the Auditorium.

 

ALLIED HEALTH/NURSING RE-ROOFING PROJECT:

  • The contractor installed the parapet wall cap along Bolivar Street . 

 

EXTERIOR/LANDSCAPING:

  • Facility Services completed connection of the piping, control wiring and tested the irrigation around the Roman St. Garage. 

 

LIONS EYE DOOR REPLACEMENT:

  • The contractor removed the existing swinging door.

 

LIBRARY COMMONS:

  • The contractor painted the restroom closets and relocated two fire alarm devices.

 

MEB 2nd FLOOR RENOVATIONS:

  • The contractor connected new fire alarm devices into the existing system.   

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor is pulling network cable for the 6th Floor conference room along. 

 

RESIDENCE HALL 2nd FLOOR LOBBY RENOVATION:  

  • The contractor continued installing the wavy ceiling grid in the expanded lobby area. 
  • The contractor installed fire alarm devices in the A & B lobby area.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continues to monitor and adjust the C Quadrant, 6th and 7th floor temporary units. 
  • The contractor completed connecting controls for roof top units 1 and 2 and air handling units 6D and 7D. 
  • Crews continued installing ductwork, piping, insulation, electrical and controls for AHUs 6C and 7C.

 

MEB MDL #3 RENOVATIONS:

  • The casework contractor installed countertop for the center island pedestal and vertical chase in all four quadrants.
  • The contractor continued installing ceiling tiles and connecting air, gas, and vacuum to the fixtures.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The contractor installed custom baseboard along the west wall of Auditorium B.
  • The A/V contractor continued work on the podium installation in Auditorium A.
  • The door hardware was installed in Auditorium A.