Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, AUGUST 11, 2009

 

1542 TULANE AVE. :

  • The contractor floated and sanded the rear wall of the 1st Floor kiosk. 
  • Facility Services continued to apply wood stain on the double-doors at the front of the 1st Floor auditorium. 
  • Quality Group moved the files and furnishings of the Departments of Family Medicine and Psychiatry to their 1st and 2nd Floor offices.

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The mechanical contractor balanced the HVAC in Auditorium A.
  • The IT group prepared the A/V system for tomorrows presentation.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring and adjusting the temporary A/C units in the A Quadrant (corner of South Roman Street and the MEB loading dock). 
  • The contractor completed piping heating hot water to AHU 6A. 
  • The control wiring for AHU 7A complete. 
  • Fire alarm wiring at AHU 6A is complete and work on 7A continues.

 

LANDSCAPING:

  • Crews began planting shrubs and plants along the Tulane Ave. side of the Roman St. Garage.

 

MEB 7TH FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor primed the walls in Room 7221. 
  • The contractor trenched the plaster walls in Rooms 7241, 7244, and 7250 to install conduits.

 

RESIDENCE HALL 2nd FLOOR LOBBY RENOVATIONS:  

  • The painting contractor continued painting the handrails on both mezzanine levels and continued taping and floating the new wall by the telephone panel.

 

RESOURCE CENTER ROOF REPLACEMENT:

  • No work was completed today due to rain and the threats of severe weather.