MONDAY, AUGUST 24, 2009

 

1542 TULANE AVE. :

  • The contractor prepped the floor in Room 122F (Womens restroom) to receive new VCT.
  • The contractor prepped Rooms 203 and 203A for mastic and insulation removal.

 

DENTAL SCHOOL AUDITORIUM A & B RENOVATIONS:

  • The A/V contractor installed and configured additional components for the podium in Auditorium B; podium 95% complete.
  • A new projector was installed in Auditorium B. 
  • The broken window glass on the 4th Floor crosswalk was replaced.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping on the Gravier Street side of the Roman Garage. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services completed shifting the temporary A/C units to the 4th and 5th Floor Quadrant D (corner of Bolivar Street and Perdido Street ) and monitored performance.
  • The contractor demolished the old air handling units 4-D and 5-D.
  • They installed new ductwork and installed new AHUs 4-D and 5-D.
  • Crews continued installing piping.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor completed installing the electrical door hardware.    
  • The contractor installed a register above the digital sign.  

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor completed roughing in the electrical for Rooms 7241 and 7250. 
  • Workers laid VCT tiles in Rooms 7221, 7241, and 7250.
  • Crews patched, taped and floated walls in Rooms 7221, 7241, and 7250   

 

ALLIED HEALTH/NURSING BLDG. REROOFING PROJECT:

  • The contractor continued trimming the main entrance canopy roof and the 4th Floor roof near the S. Roman Street side.

 

RESOURCE CENTER REROOFING PROJECT:

  • The contractor mobilized equipment on the roof.