Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, NOVEMBER 13, 2009

 

FENCE REPLACEMENT PROJECT:

  • The contractor continued installing the top and bottom rails and the fence fabric along Campus Road . 

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor replaced 8 of 23 roof drains. 
  • Crews installed wooden supports on top of the parapet wall along S. Prieur and Bolivar Streets.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services completed the installation of temporary A/C units in Quadrant D of the 2nd and 3rd Floors.
  • The contractor began selective demolition of AHU 3-D and 2-D.   

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor began the electrical rough-in in the large conference room.   

 

MEB MDL 4 RENOVATIONS:

  • The contractor continued framing up the wall and installing sheetrock along the moveable partitions supports.
  • The contractor installed the steel support for the partition track in Room 4112A.