TUESDAY, DECEMBER 15, 2009

 

1542 TULANE AVE. ADA PARKING GARAGE ENTRANCES:

  • The contractor painted the hand rails on the 1st Floor. 
  • The contractor roughed in and mounted the fire alarm devices at the 2nd Floor entrance.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C in Quadrant C of the 2nd and 3rd Floors.
  • The contractor completed electrical and controls installation on AHU 2-C.
  • They continued the ductwork installation on AHU 2-B and the duct work and exhaust fan installation in mechanical room 2-A.
  • Crews continued the electrical and controls installation on AHU 3-C and the installation of new electrical conduit in mechanical room 3-A. 

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

  • The contractor continued installing metal studs for the laboratory walls.

 

MEB AUTOPSY HVAC UPGRADE:

  • The contractor relocated sprinkler heads in the autopsy room.

 

MEB SEMINAR ROOM A/V INSTALLATION:

  • The contractor installed the A/V screen and the ceiling in Seminar Room 6.
  • Their workers installed the A/V screen in Seminar Room 4.