Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JANUARY 12, 2010

ALLIED HEALT/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor removed lights and electrical conduit on the 1st Floor.

EXTERIOR/LANDSCAPING:

  • Facility Services laid sod along Bolivar and South Roman Streets adjacent to the Residence Hall.

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

  • The contractor continued to run electrical conduit in the lab.
  • Workers continued to tape and float the interior walls.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued hanging brackets for the large conference room lights.

RESOURCE CENTER ROOF REPLACEMENT PROJECT:

  • The contractor installed the parapet wall cap on the main elevator penthouse and installed the counter flashing along Roman Street.

MEB AHU REPLACEMENT PROJECT:

  • Facility Services continued monitoring the temporary air conditioning serving the cafeteria kitchen area.
  • The contractor completed installing chilled water piping for AHU 3-A.
  • They continued installing piping for AHU 2-A and began the electrical and controls work on AHU 2-A.

MEB MORGUE HVAC UPGRADE:

  • The contractor removed one autopsy table in the room in preparation for installing the new table.