Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JANUARY 19, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to remove ceiling and metal studs from the 1st Floor on the Bolivar St. side of the building.

LIONS/LSU CLINIC BLDG 7TH FLOOR LAB RENOVATIONS:

  • The electrical contractor continued to run electrical conduit in the new lab space.
  • The contractor started running the new ductwork in the lab.

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The electrical contractor ran additional conduit.
  • The contractor installed ductwork in the large conference room.

MEB AHU REPLACEMENT PROJECT:

  • Facility Services continued monitoring the temporary air conditioning serving the cafeteria kitchen area.
  • The contractor completed insulating chilled and hot water piping for AHU 3-A and 3-B.
  • Work continues on the electrical wiring and controls for AHU 2-A and AHU 3-A.
  • The Inspecting Engineer and the contractor began the building walk through and inspection.
  • They completed their inspection of the Roof Top Units, and all AHUs on the 5th through 7th Floors.

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:

  • The contractor installed glazed blocks to close the wall by the stairwell.

MEB MDL #4 RENOVATIONS:

  • The contractor installed doors in Room 4210.
  • They installed cove base in the main MDL room and Room 4210.

RESOURCE CENTER ROOF REPLACEMENT PROJECT:

  • The contractor primed and painted all doors and door frames.
  • Workers continued installing the lightning protection.