Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MARCH 4, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued the demolition in Rooms 211, 212, 233 and 236.
  • Crews continued installing electrical conduit in the main corridor on the 1st Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to run conduit for the new ATS room.
  • They installed new copper lines for the sump pump on the 1st Floor.
  • Workers removed ceiling grid on the 1st Floor, Bolivar Street side.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor completed the pile driving.

FENCE REPLACEMENT PROJECT:

  • The contractor removed 8 more forms from the monumental columns. 24 of 25 columns have been poured.
  • The crew set up the form for the final column.

EXTERIOR/LANDSCAPING:

  • Facility Services planted shrubs in the planting beds on the Administration Building side of the horseshoe.