Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, APRIL 21, 2010

LANDSCAPING/EXTERIOR:

  • Facility Services continued grading on the Florida Avenue side of the School of Dentistry Clinic Building.

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor is laying CMU block for the restrooms along the Gravier Street side of the 1st Floor.
  • The ceiling in the Tiger Room was removed.

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

  • The contractor completed installing the new laboratory casework.

FENCE REPLACEMENT PROJECT:

  • The contractor laid and leveled the sand base course for the remaining section of new sidewalk along Florida Avenue connecting to the horseshoe drive.
  • Crews installed a grate drain at the horseshoe and installed rebar for the replacement concrete.

DENTAL SCHOOL NORTH FIELD GRADING:

  • The contractor has completed 75 percent of the rough grading and continues cutting to the final grade contours.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing underground electrical conduit near the old switchgear.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor chipped out the floor for the fuel line penetrations on the 4th and 5th Floors.
  • The construction of the temporary elevator shaft wall is proceeding.