Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MAY 17, 2010

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor installed four valves in the chilled water system in preparation for the installation of the elevated equipment.

·         Workers ran conduit from the new ATS room to the pump room on the 2nd Floor.

·         The concrete forms were removed from the new waterproof walls constructed for Elevators 3 and 4.

 

CEB COVERED WALKWAY:

·         The contractor started setting up the abatement containment area.

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

·         The contractor continued working on the remaining punch list items.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The AV contractor installed fiber cable for the speakers, microphone and projector in the large conference room, and for the dimmer panel in the AV room.