WEDNESDAY, JUNE 2, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits along the steel beams.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor finished constructing the concrete forms and began installing steel rebar for the second level slab.
  • They continued trenching on the S. Roman Street side of the parking area and installed additional electrical conduits underground.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor started excavating for the storm drain pipe and placing the drain pipe in the trenches.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor installed ceiling tiles in the small conference room, offices area, and the corridor area.
  • The soffit outside the large conference room was painted.

CEB COVERED WALKWAY:

  • The contractor continued to fill and grade the site at the patio location.