ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor made the final welded connections for the structural steel.
  • Crews continued to run fire alarm cables to the 2nd Floor fire alarm panel.
  • Two new pumps have been delivered to the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing underground plumbing near the C Tower storage room on the Bolivar Street side.
  • Crews continued building the concrete forms for the roof of the new structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to install the elevator pit parts for Elevator 3 and 4.
  • They continued fabricating the chilled water bypass piping in the 2nd Floor pump room.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued preparing the base course; installing the geo-textile fabric and laying the limestone base material.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor installed ceiling tiles in the large conference room.
  • The AV contractor installed speakers in the large conference room.

CEB COVERED WALKWAY:

  • The contractor continued to drive piles for the sidewalk. Five piles remain to be driven.