Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JUNE 22, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the final connections for the new structural steel.
  • Crews continued to run fire alarm cables to the 2nd Floor fire alarm panel.
  • They continued installing CMU walls and started forming up the elevator wall.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing underground plumbing near the C Tower storage room on Bolivar Street side.
  • The contractor continued building forms for the roof of the new enclosure until rain interrupted their work.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to install the elevator pit parts for Elevators 3 and 4.
  • They completed installing conduits through the floor in the new switchgear room.
  • A concrete form was constructed for the pad that will be used to support the electrical transformer in the ATS room.
  • 17 abandoned data cables were removed from the 2nd Floor pump room.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued to excavate the west side of the lot and grade and back-fill the east side of the lot.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor pulled wire for the electrical panel in the mechanical room.
  • New tile was laid in the elevator lobby.

CEB COVERED WALKWAY:

  • No piles were driven today due to the inclement weather.