Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JUNE 25, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continues to run fire alarm cables to the 2nd Floor fire alarm panel.
  • Concrete for the elevator shaft wall was poured.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor core drilled in the grade beam for plumbing near the C Tower storage room on the Bolivar Street side.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continues to install the elevator pit parts for Elevators 3 and 4.
  • A CMU wall was constructed in the new switchgear room on the 2nd Floor.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continues laying floor tiles in the elevator lobby and began grouting the new tiles.