Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JUNE 8, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued pulling the fire alarm cables to the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued trenching on the South Roman side.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began removing the temporary shaft wall for Elevators 3 and 4.
  • Crews began running the electrical control wires to the ATS Room.
  • A temporary construction wall was erected in the Bookstore.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued grading the site in preparation for the underground electrical installation. The excavated materials are being removed from the site.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor relocated the ductwork in the large conference room.

CEB COVERED WALKWAY:

  • The contractor began surveying the site to determine the locations for the wood piles.