THURSDAY, JULY 1, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continues to run fire alarm cables to the 2nd Floor fire alarm panel.
  • They continue removing the mechanical room CMU wall on the 2nd floor.
  • Crews continue to run conduit and set the housing for the relocation of electrical panel D1A.
  • The contractor set the sump pump for Elevators 1, 2, and 3.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor completed installing underground electrical conduits by the C Tower, Roman Street side and back filled the trench.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the main switch board and the emergency panel in the new switchgear room on the 2nd Floor.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued to install light fixtures throughout the space.
  • The AV contractor ran additional cable to the podium in the large conference room.