Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JULY 14, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The general contractor applied the 5th and final coat of fire proofing to the structural steel beams.
  • The contractor re-installed the granite panels surrounding the elevator lobby.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The mechanical contractor poured the concrete pad for the AHU in the 1st Floor mechanical room.
  • The contractor ran electrical conduit in the 8th Floor electrical room.
  • Crews laid CMU block for Elevators 1 & 2 on the 1st Floor.
  • The roofing contractor began erecting roof curbs for the emergency generator.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing the new electrical duct bank in the main driveway.
  • The contractor continued installing steel reinforcement in the concrete forms for the roof of the new enclosure.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor began laying the asphalt paving and completed the base course.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued painting walls.