Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JULY 15, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing granite panels surrounding the elevator lobby.
  • The elevator sub-contractor started installing pit parts for Elevators 1-3.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing electrical conduit in the 8th Floor electrical room.
  • The general contractor constructed the temporary shaft wall for Elevators 1 & 2 on the 1st Floor.
  • The roofing contractor continued erecting the roof curbs for the emergency generator.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing the new electrical duct bank in the main driveway.
  • The concrete for the roof of the new enclosure was poured.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor completed laying the wearing course on the parking lot.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor finished installing the lighting dimmer panel.
  • The AV contractor installed the projection screen in the large conference room.