Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 11, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued removing elevator pit parts.
  • Crews continued removing the heat exchanger.
  • Duct work was removed from the 2nd Floor.
  • The contractor installed the CMU in the Tiger Room.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor removed insulation from the existing chilled water lines in the 2nd Floor pump room.
  • Workers are cleaning the 1st Floor AHUs.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 3 additional precast panels on the 2nd level of the elevated enclosure.
  • 19 of the 40 panels have now been installed.

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor installed access control wire in the large conference room.