Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, AUGUST 12, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • Workers continued removing elevator pit parts from the freight elevator.
  • They continued working on removing the heat exchanger,
  • Crews started welding new heating hot water lines.
  • 2 heating hot water pumps were set.
  • The contractor installed additional CMU in the Tiger Room and in both stairwells along Bolivar Street.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION

  • The contractor removed the chilled water pumps from the 2nd Floor pump room.
  • They continued to clean the 1st Floor AHUs.
  • The contractor continued to remove paint from the 1st Floor walls.
  • Bus duct was installed through the 2nd Floor slab from the new switchgear.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION

  • Inclement weather prevented work at the site.

LION/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor continued installing access control wiring in the large conference room.