ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor finished removing the heating hot water lines.
  • Workers continued installing concrete forms for the elevator shaft wall.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • 4 additional precast panels were installed on the 2nd Floor and roof level of the elevated enclosure.
  • 36 of the 40 panel are in place.
  • The contractor installed exhaust pipes penetrating the roof for the fire pump and the generator.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • Crews continued to remove paint from the 1st Floor walls.
  • The contractor continued to remove chilled water pipe from the 2nd Floor pump room.
  • They began installing the pit parts for Elevators 1 & 2.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The final inspection was completed.