Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, AUGUST 20, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing the metal lathe for the stucco walls in the Tiger Room.
  • The mechanical contractor began fabricating the chilled water lines for the 2nd Floor.
  • The contractor removed the wooden forms from the elevator pit walls.
  • The electrical contractor provided power to the new domestic water pumps and removed a 480V electrical distribution panel from the old 2nd Floor pump room.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the last 2 precast panels on the elevated enclosure. All 40 panels have been installed.
  • Crews continue the finish welding of the precast panels.
  • The electrical contractor continued installing electrical conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the pit parts for Elevators 1 & 2.