Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, AUGUST 23, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing the metal lathe for the stucco walls in the Tiger Room.
  • The mechanical contractor continued fabricating chilled water fittings for the 2nd Floor.
  • The contractor installed foam board and rebar for the rear elevator shaft wall.
  • Workers set the c-channel for 10 storefronts and set 1 of 19 storefronts on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing electrical conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The work has been completed on Elevators 1 & 2. They passed inspection and are back in normal operation.
  • The contractor continued painting the 1st Floor walls.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The AV contractor installed the podium and projector in the small conference room and one projector in the large conference room.

CEB COVERED WALKWAY:

  • The contractor started fabricating the rebar for the walkway footings and setting up forms for the footings near the side entrance to the building.