Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, SEPTEMBER 1, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing the metal lathe for the stucco walls in Room 147.
  • The contractor continued welding connections for the chilled water lines on the 2nd Floor and installed an additional 20 feet of chilled water lines.
  • They continued installing CMU block surrounding the storefronts and on the stairwell along Roman Street.
  • The contractor re-installed the marble in the elevator lobby.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor set concrete forms for the parking islands on the ground floor.
  • The 4 roof drains were installed.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued to install bus duct in the switchgear.

CEB COVERED WALKWAY:

  • The contractor started digging footers and installing rebar along the length of the walkway.