Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, SEPTEMBER 14, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
  • The contractor continued making fittings for the chilled water and heating hot water lines.
  • Chilled water lines were installed near the stairwell.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor poured concrete for the equipment pads on the 2nd Floor.
  • The electrical contractor continued installing conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor poured the concrete elevator shaft wall between Elevators 2 and 3.
  • The electrical contractor continued to install lugs in the switchgear.
  • The contractor continued to prime walls on the 1st floor.