ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing the metal lathe for the stucco walls in Stairwells A and B.
  • The contractor welded the chill water saddles in preparation of the chilled water tie-ins.
  • They ran heating hot water lines at the walkway entrance.
  • Workers continued cleaning return air grilles and applied the second of two anti-microbial duct coatings.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued removing the temporary elevator shaft wall in the elevator pit.
  • They continued to prime walls in the mail room.

CEB COVERED WALKWAY:

  • The contractor completed setting wooden forms for the walkway at the Claiborne Avenue entrance to the District Entergy parking garage.