Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, OCTOBER 25, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued applying the 3rd coat of stucco to the Tiger Room and the 1st coat to the walls above the storefronts along Bolivar Street. 
  • Workers continued fabricating heating hot water lines for the 2nd Floor.
  • They are setting the first re-built AHU on the 1st Floor.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor completed installing flashing cap sheet around the steel platform columns and the conduit penetrations on the roof.
  • They are installing conduits from the transformer to the disconnect panels on the steel platform on the roof.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor applied the 2nd coat of plaster in Rooms 122A, 125A, and 125B.
  • Workers removed the wooden concrete forms from the freight elevator shaft wall.

CSRB EXHAUST UPGRADE: