Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, NOVEMBER 15, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing framing for the 2nd floor auditorium along the Gravier Street side of the building.  
  • Workers are insulating the heating hot water lines.
  • They continued installing copper piping for the AHU in the 2nd Floor mechanical room.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued pulling wires for the switchgear on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to install elevator pit parts in the freight elevator.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor removed brick pavers near the existing generator in preparation for excavation.

CSRB EXHAUST UPGRADE:

  • The contractor cut floor penetrations in the 3rd Floor mechanical room for exhaust duct riser #3.